BS ISO 4917-6:2024
$102.76
Design of nuclear power plants against seismic events – Post-seismic measures
Published By | Publication Date | Number of Pages |
BSI | 2024 | 22 |
PDF Catalog
PDF Pages | PDF Title |
---|---|
2 | undefined |
6 | Foreword |
7 | Introduction |
9 | 1 Scope 2 Normative references 3 Terms and definitions |
10 | 4 Procedure 4.1 General requirements 4.2 Verification of the earthquake |
11 | 4.3 Classification of the earthquake 4.4 Initial measures 4.4.1 Plant check-up from the control room and plant walk-down inspection (Figure 2, chart item 3) |
12 | 4.4.2 Deviations caused by the earthquake (Figure 2, chart item 4) 4.4.3 Specified normal operation condition in accordance with the operating manual (Figure 2, chart item 5) 4.5 In-depth measures 4.5.1 General 4.5.2 Special/Seismic inspections and analyses (Figure 2, chart item 6) |
13 | 4.5.3 Specified normal operation condition and permissible loads (Figure 2, chart item 7) 4.5.4 Shutdown inspection (Figure 2, chart item 9) 4.6 Resulting measures 4.6.1 Continued operation (Figure 2, chart item 8) 4.6.2 Shutting down the plant (Figure 2, chart item 10) |
14 | 4.6.3 Additional procedures (Figure 2, chart item 11) |
15 | Annex A (informative) Derivation of factor, f |
17 | Annex B (informative) Directives for plant walk-down inspections |
18 | Annex C (informative) Special/Seismic inspections |
20 | Bibliography |